Contractor: Sierra-Nevada Construction
This project involves construction of a new frontage roadway that parallels the
south side of Highway 99. The project will begin at Maple Avenue and connect to
Garrison Way (near the new Horizon Business Park, west of the Fulton Overpass).
The new road will be extended through the existing Fulton Overpass using a
pre-cast bridge system.
Update (04/16/2008):
Sierra-Nevada has begun construction on this project. As part of this work, the
project will include a new bridge structure; which will require the Wilma/Fulton
Avenue Overpass be closed for a period of time, while the new structure is being
built. However, the Wilma Avenue Roundabout will remain open, with full access
to all streets, except the overpass, throughout construction. Construction on
the bridge structure has been delayed. Signs will be posted at both sides of the
Fulton overpass as soon as a new closure date has been established. Once
construction begins the overpass is anticipated to be out of service for
approximately ninety (90) days. Please view the detour map for directions while
the overpass is out of service.
For questions about this project please contact
Barbara Schneider at (209) 599-2108 or by email at
bschneider@cityofripon.org.
[South Frontage Road Phase II Schedule]
Move your curser over the small image to enlarge the picture.
|